A tower packing RFQ does not need to be a complete process design package.

But it should contain enough information for a supplier to understand exactly what needs to be quoted and which technical points still require confirmation.

A request such as:

“Please quote 50 mm Pall Rings.”

may be enough to obtain a unit price.

It is usually not enough to determine whether the packing is suitable for the tower.

The DAIER Tower Packing Engineering Assistant can help organize preliminary project data before the inquiry is sent.

The next step is turning that result into a quote-ready RFQ.


What Is a Quote-Ready Tower Packing RFQ?

A quote-ready RFQ clearly separates three types of information:

1. What Is Already Confirmed

For example:

packing type

packing size

material

required quantity

tower dimensions

2. What Still Needs Supplier Review

For example:

suitable packing size

material compatibility

alternative packing model

packing quantity

replacement option

3. Commercial Requirements

For example:

delivery destination

required delivery time

quotation term

packing requirement

required documents

This distinction is important.

The supplier should immediately understand whether the buyer wants:

a price for an already specified product

or

a technical recommendation plus quotation.


Step 1 — Start with the Engineering Assistant Result

Before preparing the RFQ, review the preliminary result from the DAIER Tower Packing Engineering Assistant.

Confirm whether it contains:

tower diameter

packing bed height

preliminary packing volume

packing family

packing size direction

material direction

preliminary weight information

missing technical data

If you are unsure how to read the result, see:

How to Interpret Results from the DAIER Tower Packing Engineering Assistant

Do not copy the result into an RFQ without checking the original input data first.


Step 2 — State the Project Type

The supplier should know immediately what kind of project is being quoted.

Examples include:

new packed tower

replacement packing

tower revamp

capacity increase

maintenance replacement

pressure-drop improvement

fouling improvement

material upgrade

A replacement project should be identified clearly because existing packing and tower internals may affect the recommendation.

For replacement projects, see:

How to Use the DAIER Tower Packing Engineering Assistant for an Existing Tower Replacement


Step 3 — Give the Exact Packing Requirement If It Is Already Known

If the project specification is already fixed, state it directly.

For example:

Product: Plastic Pall RingSize: 50 mmMaterial: PPQuantity: 8 m³

In this situation, the supplier mainly needs to confirm:

product availability

technical specification

price

delivery time

packing method

commercial terms

Do not unnecessarily ask the supplier to redesign a packing selection that has already been specified by the EPC or end user.


Step 4 — If the Packing Is Not Fixed, Say So Clearly

Sometimes the buyer knows the tower conditions but does not know which packing should be selected.

In that case, write:

Packing type and size are not fixed. Please review the operating data and recommend a suitable preliminary option.

Then provide the available engineering information.

This avoids a common misunderstanding:

The supplier should not assume that a packing mentioned in an early discussion is already the final specification.


Step 5 — Include Tower Dimensions

For quantity calculation and preliminary screening, include:

tower internal diameter

packing bed height

number of packed beds

If there are several packed sections, list them separately.

Example:

Tower ID: 1,800 mmBed 1 Height: 2,500 mmBed 2 Height: 3,000 mmNumber of Beds: 2

If the Engineering Assistant has already calculated the approximate packing volume, include both the dimensions and the result.

Do not send only the calculated cubic meters if tower dimensions are available.

The dimensions allow the supplier to check the quantity basis.


Step 6 — Include the Main Operating Conditions

If technical screening is required, include the available process conditions.

Useful information includes:

gas flow

liquid flow

operating temperature

operating pressure

gas composition

liquid composition

solids or fouling conditions

process application

If some information is unavailable, write:

Not available at this stage

rather than guessing.

For the full engineering-input list, see:

Tower Packing Selection Parameters


Step 7 — State the Process Application

Do not send only numbers.

Tell the supplier what the packed tower is doing.

Examples:

acid gas absorption

wet gas scrubbing

stripping

distillation

wastewater treatment

odor control

gas purification

cooling

The application provides context for the operating data.

For example, a dirty scrubber and a clean distillation column may prioritize very different packing characteristics even if their tower dimensions are similar.


Step 8 — For Replacement Projects, Include the Existing Packing

If the project involves an existing tower, include:

existing packing type

existing packing size

existing material

packing bed height

current operating problem

If available, also attach:

photographs

old drawings

packing datasheets

tower internal drawings

The supplier needs to understand whether the objective is:

same replacement

or

performance improvement.

These are different RFQs.


Step 9 — Explain the Problem You Want to Solve

This is one of the most valuable pieces of information in a revamp RFQ.

Examples:

Current packing has frequent blockage.

Pressure drop has increased significantly.

Existing packing is corroded.

Plant capacity will be increased.

We want to reduce pressure drop.

Existing packing model is no longer available.

This tells the supplier what the proposed replacement is expected to improve.

Without this information, an “equivalent replacement” may simply reproduce the same problem.


Step 10 — Confirm Whether Tower Internals Are Included

Packing RFQs often become unclear because nobody states whether tower internals are part of the quotation.

Confirm whether the quotation should include:

packing only

packing support grid

support plate

hold-down grid

retaining ring

liquid distributor

redistributor

other tower internals

For existing towers, also provide the manway size when new internals may be required.

Large internals may need to be manufactured in segments for installation.


Step 11 — Add Quantity or Ask the Supplier to Confirm It

There are two valid RFQ situations.

Quantity Already Known

Example:

Required Quantity: 12 m³

The supplier quotes based on this quantity.

Quantity Needs Confirmation

Example:

Tower ID: 2,000 mmPacking Bed Height: 4,000 mmPlease confirm the required packing quantity.

The Engineering Assistant can provide a preliminary packing-volume estimate, but the dimensions should still be included in the RFQ.


Step 12 — Add Material Requirements

If the material is already specified, state it clearly.

Examples:

PP

PVDF

SS304

SS316L

ceramic

If the material is not fixed, ask for a recommendation based on the actual medium and temperature.

Example:

Material is not fixed. Please review compatibility with the following process conditions.

Then provide:

chemical composition

concentration

temperature

pressure

Do not allow price alone to determine the packing material.


Step 13 — State Required Technical Documents

If project documentation is required, include it in the RFQ rather than asking after the quotation is completed.

Possible requirements include:

datasheet

dimensional drawing

material information

packing bulk density

specific surface area

void fraction

certificate of analysis

material certificate, where applicable

packing photographs

installation information

Not every project requires every document.

Ask only for documents relevant to the project.


Step 14 — Include Delivery Information

A supplier cannot prepare a meaningful freight quotation without knowing where the goods are going.

Include:

destination country

destination port or city

required Incoterm, if known

required delivery date

whether freight quotation is required

Examples:

EXW quotation required

or:

Please quote CIF Busan, Korea

or:

Please provide product price first; freight will be confirmed separately.

This keeps the technical quotation and logistics requirement clear.


Step 15 — Ask for the Information You Actually Need in the Quotation

A good RFQ tells the supplier what the response should contain.

For example:

Please provide:

recommended packing model

size

material

unit price

total price

required quantity

bulk density

estimated net weight

lead time

packing method

quotation validity

technical datasheet

This makes quotations easier to compare between suppliers.


Example: Weak RFQ vs Quote-Ready RFQ

Weak RFQ

Please quote PP Pall Ring 50 mm.

The supplier still does not know:

quantity

application

tower size

destination

whether 50 mm is fixed

whether technical review is required


Quote-Ready RFQ

Project: Existing scrubber packing replacementTower ID: 1,500 mmPacking Bed Height: 3,000 mmExisting Packing: 50 mm PP Pall RingProcess: Wet gas scrubbingOperating Temperature: 55°COperating Pressure: AtmosphericGas Flow: 9,000 m³/hLiquid Flow: 25 m³/hCurrent Problem: Increasing pressure drop and visible foulingMaterial: PP preferredRequirement: Please review whether 50 mm Pall Ring should be retained or whether a more open packing should be considered.Quotation Required: Packing, technical datasheet, quantity, weight, lead time and packing dimensions.

This RFQ gives the supplier enough context to decide whether the request is simply commercial or requires engineering review.


A Practical RFQ Structure

When preparing a tower packing inquiry, organize it into six sections:

A. Project

New tower / replacement / revamp

Application

Project objective

B. Tower

Internal diameter

Bed height

Number of beds

Manway size if relevant

C. Process

Gas flow

Liquid flow

Temperature

Pressure

Composition

Fouling or solids

D. Packing

Type

Size

Material

Quantity

Existing packing if applicable

E. Tower Internals

Support included or excluded

Hold-down included or excluded

Distributor included or excluded

F. Commercial

Delivery destination

Incoterm

Required delivery time

Required documentation

This structure is usually easier to review than placing all project information inside one paragraph.


What If Some RFQ Data Are Missing?

Do not delay every inquiry until every process parameter is available.

Instead, separate:

Known

from

Unknown

and

To Be Confirmed by Supplier / Engineer

For example:

Tower ID: ConfirmedBed Height: ConfirmedGas Flow: ConfirmedLiquid Flow: Not availablePacking Type: Supplier recommendation requiredMaterial: PP preferred, compatibility to be reviewed

This allows preliminary communication to begin without pretending that incomplete engineering data are complete.


Use the Engineering Assistant Before Sending the RFQ

The DAIER Tower Packing Engineering Assistant can be used as a preparation step before requesting quotation.

A practical workflow is:

1. Enter the available project data

2. Review the preliminary packing direction

3. Calculate or confirm packing volume

4. Identify missing information

5. Convert the result into the RFQ structure

6. Send the RFQ for supplier and engineering review

The tool therefore does not replace the RFQ.

It helps make the RFQ more complete.


From Engineering Screening to Quotation

A good tower packing RFQ should allow the supplier to answer three questions quickly:

What exactly should be quoted?

Packing type, size, material and quantity.

What engineering issue needs to be reviewed?

Selection, replacement, pressure drop, fouling, capacity or material compatibility.

What commercial information is required?

Price, lead time, documentation, packing and delivery terms.

When these three areas are clear, the quotation process becomes much more efficient.

If you have already completed a preliminary screening, use:

How to Interpret Tower Packing Engineering Assistant Results

If you want to understand what the tool calculates, see:

What Does the DAIER Tower Packing Engineering Assistant Calculate?

Use the DAIER Tower Packing Engineering Assistant

Specs and test data available upon request.

How to Compare Tower Packing Options with the DAIER Engineering Assistant

How to Use the DAIER Tower Packing Engineering Assistant for an Existing Tower Replacement